— Project Summary

Queue ID
GrantPUD-1
Capacity
120 MW
Technology
Solar+Battery
Status
active
Location
Grant, WA
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBatteryGrantPUDLBNL

120 MW hybrid in Grant, WA · In queue since September 2017

120 MW

Capacity

1

Components

Solar

8y 6m

In Queue

IA Executed

IA Status

Interconnection Timeline

Total Duration

8y 6m

Construction75%
Queue EntrySep 1, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Commercial operation date not yet determined

Project Details

State

WA

County

Grant

Region

West

Developer

Utility

Grant County Public Utility District

Entity

GrantPUD

Point of Interconnection

Rocky Ford - Larson 115kV or 230 kV line

Data Source

LBNL

No news available for this project.