BetaActiveBatteryFPLLBNL
150 MW storage in Bay, FL · In queue since January 2024 · Proposed COD January 2026
150 MW
Capacity
1
Components
Battery
2y 2m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2 years
Schedule
2 months past proposed COD
Impact Study25%
Queue EntryJan 8, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-01-31
Project Details
State
FL
County
Bay
Region
Southeast
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
Lansing Smith Plant - Bay County
Data Source
LBNL