BetaActiveBatteryFPLLBNL
100 MW storage in Putnam, FL · In queue since January 2024 · Proposed COD January 2027
100 MW
Capacity
1
Components
Battery
2y 2m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3 years
Impact Study25%
Queue EntryJan 8, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-01-31
Project Details
State
FL
County
Putnam
Region
Southeast
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
Putnam Plant
Data Source
LBNL