— Project Summary

Queue ID
FPL-615
Capacity
100 MW
Technology
Battery
Status
active
Location
Putnam, FL
Region
Southeast
Developer
FPL
IA Status
System Impact Study

BetaActiveBatteryFPLLBNL

100 MW storage in Putnam, FL · In queue since January 2024 · Proposed COD January 2027

100 MW

Capacity

1

Components

Battery

2y 2m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3 years

Impact Study25%
Queue EntryJan 8, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-01-31

Project Details

State

FL

County

Putnam

Region

Southeast

Developer

FPL

Utility

Florida Power & Light

Entity

FPL

Point of Interconnection

Putnam Plant

Data Source

LBNL