74.9 MW generation in Desoto, FL · In queue since December 2023 · Proposed COD April 2033
74.9 MW
Capacity
1
Components
Solar
2y 3m
In Queue
System Impact Study
IA Status
COD target: 2033
Interconnection Timeline
Total Duration
9y 4m
Impact Study25%
Queue EntryDec 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2033-04-30
Project Details
State
FL
County
Desoto
Region
Southeast
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
Desoto County
Data Source
LBNL