BetaActiveSolarFPLLBNL
74.5 MW generation in Hendry, FL · In queue since July 2023 · Proposed COD October 2033
74.5 MW
Capacity
1
Components
Solar
2y 8m
In Queue
System Impact Study
IA Status
COD target: 2033
Interconnection Timeline
Total Duration
10y 3m
Impact Study25%
Queue EntryJul 25, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2033-10-31
Project Details
State
FL
County
Hendry
Region
Southeast
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
State Road 80
Data Source
LBNL
No news available for this project.