BetaActiveSolarFPLLBNL
74.9 MW generation in Bradford, FL · In queue since February 2023 · Proposed COD January 2031
74.9 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Facility Study
IA Status
COD target: 2031
Interconnection Timeline
Total Duration
7y 11m
Facilities Study50%
Queue EntryFeb 23, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2031-01-17
Project Details
State
FL
County
Bradford
Region
Southeast
Developer
Third Party
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
Deerhaven (GVL)-Bradford 138kV
Data Source
LBNL
No news available for this project.