74.5 MW generation in Manatee, FL · In queue since January 2023 · Proposed COD July 2033
74.5 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Facility Study
IA Status
COD target: 2033
Interconnection Timeline
Total Duration
10y 6m
Facilities Study50%
Queue EntryJan 6, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2033-07-31
Project Details
State
FL
County
Manatee
Region
Southeast
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
Near Myakka City
Data Source
LBNL