— Project Summary

Queue ID
FPL-489
Capacity
74.5 MW
Technology
Solar
Status
active
Location
Calhoun, FL
Region
Southeast
Developer
FPL
IA Status
Facility Study

BetaActiveSolarFPLLBNL

74.5 MW generation in Calhoun, FL · In queue since August 2022 · Proposed COD January 2026

74.5 MW

Capacity

1

Components

Solar

3y 7m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 5m

Schedule

2 months past proposed COD

Facilities Study50%
Queue EntryAug 9, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-01-31

Project Details

State

FL

County

Calhoun

Region

Southeast

Developer

FPL

Utility

Florida Power & Light

Entity

FPL

Point of Interconnection

Smith- Sinai Cemetery 230kV line

Data Source

LBNL

No news available for this project.