BetaActiveSolarFPLLBNL
74.5 MW generation in Highlands, FL · In queue since July 2022 · Proposed COD July 2029
74.5 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
7 years
Facilities Study50%
Queue EntryJul 20, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-07-31
Project Details
State
FL
County
Highlands
Region
Southeast
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
SR70 Sweat-Whidden 230kV
Data Source
LBNL
No news available for this project.