FPL-465
Capacity
74.5 MW
Technology
Solar
Status
active
Location
Collier, FL
Region
Southeast
Developer
FPL
IA Status
Facility Study

BetaActiveSolarFPLLBNL

74.5 MW generation in Collier, FL · In queue since April 2022 · Proposed COD January 2029

74.5 MW

Capacity

1

Components

Solar

3y 11m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

6y 9m

Facilities Study50%
Queue EntryApr 21, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-01-31

Project Details

State

FL

County

Collier

Region

Southeast

Developer

FPL

Utility

Florida Power & Light

Entity

FPL

Point of Interconnection

Collier County

Data Source

LBNL