BetaActiveSolarFPLLBNL
74.5 MW generation in Indian River, FL · In queue since April 2022 · Proposed COD January 2029
74.5 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 9m
Facilities Study50%
Queue EntryApr 6, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-01-31
Project Details
State
FL
County
Indian River
Region
Southeast
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
Northern St. Lucie County
Data Source
LBNL
No news available for this project.