BetaActiveSolarFPLLBNL
74.5 MW generation in Desoto, FL · In queue since March 2022 · Proposed COD January 2028
74.5 MW
Capacity
1
Components
Solar
4 years
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 10m
Facilities Study50%
Queue EntryMar 2, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-01-31
Project Details
State
FL
County
Desoto
Region
Southeast
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
Whidden Sub
Data Source
LBNL
No news available for this project.