BetaActiveSolarFPLLBNL
24.5 MW generation in Miami-Dade, FL · In queue since February 2022 · Proposed COD January 2025
24.5 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 11m
Schedule
14 months past proposed COD
Facilities Study50%
Queue EntryFeb 25, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-31
Project Details
State
FL
County
Miami-Dade
Region
Southeast
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
Davis-Florida City #2 138kV
Data Source
LBNL
No news available for this project.