— Project Summary

Queue ID
FPL-425A
Capacity
75 MW
Technology
Solar+Battery
Status
active
Location
Jackson, FL
Region
Southeast
Developer
Third Party
IA Status
Facility Study

BetaActiveSolarBatteryFPLLBNL

75 MW hybrid in Jackson, FL · In queue since February 2022 · Proposed COD March 2029

75 MW

Capacity

1

Components

Solar

4y 1m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

7y 1m

Facilities Study50%
Queue EntryFeb 7, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-03-01

Project Details

State

FL

County

Jackson

Region

Southeast

Developer

Third Party

Utility

Florida Power & Light

Entity

FPL

Point of Interconnection

Holmes Creek-Highlands City 230kV

Data Source

LBNL