BetaActiveSolarFPLLBNL
74.5 MW generation in Leon, FL · In queue since August 2021 · Proposed COD July 2028
74.5 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 11m
Facilities Study50%
Queue EntryAug 5, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-31
Project Details
State
FL
County
Leon
Region
Southeast
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
Raven - Sinai 161kV line
Data Source
LBNL
No news available for this project.