— Project Summary

Queue ID
FPL-417
Capacity
76 MW
Technology
Gas
Status
active
Location
Volusia, FL
Region
Southeast
Developer
FPL
IA Status
Facility Study

BetaActiveGasFPLLBNL

76 MW generation in Volusia, FL · In queue since September 2020 · Proposed COD December 2024

76 MW

Capacity

1

Components

Gas

5y 6m

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

4y 3m

Schedule

16 months past proposed COD

Facilities Study50%
Queue EntrySep 18, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-01

Project Details

State

FL

County

Volusia

Region

Southeast

Developer

FPL

Utility

Florida Power & Light

Entity

FPL

Point of Interconnection

Sanford Sub

Data Source

LBNL

No news available for this project.