— Project Summary

Queue ID
FPL-398
Capacity
74.5 MW
Technology
Solar
Status
active
Location
Putnam, FL
Region
Southeast
Developer
FPL
IA Status
Facility Study

BetaActiveSolarFPLLBNL

74.5 MW generation in Putnam, FL · In queue since July 2020 · Proposed COD July 2030

74.5 MW

Capacity

1

Components

Solar

5y 8m

In Queue

Facility Study

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

10 years

Facilities Study50%
Queue EntryJul 21, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-07-31

Project Details

State

FL

County

Putnam

Region

Southeast

Developer

FPL

Utility

Florida Power & Light

Entity

FPL

Point of Interconnection

Carter-Duval

Data Source

LBNL

No news available for this project.