— Project Summary

Queue ID
FPL-380D
Capacity
20 MW
Technology
Solar
Status
active
Location
Calhoun, FL
Region
Southeast
Developer
Third Party
IA Status
IA Executed

BetaActiveSolarFPLLBNL

20 MW generation in Calhoun, FL · In queue since February 2020 · Proposed COD October 2027

20 MW

Capacity

1

Components

Solar

6y 1m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 8m

Construction75%
Queue EntryFeb 27, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-10-15

Project Details

State

FL

County

Calhoun

Region

Southeast

Developer

Third Party

Utility

Florida Power & Light

Entity

FPL

Point of Interconnection

Altha - Gaskin (PS) 115kV line

Data Source

LBNL