20 MW generation in Calhoun, FL · In queue since February 2020 · Proposed COD October 2027
20 MW
Capacity
1
Components
Solar
6y 1m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-10-15
State
FL
County
Calhoun
Region
Southeast
Developer
Third Party
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
Altha - Gaskin (PS) 115kV line
Data Source
LBNL
Control of $2.5M in public money is latest dispute at shuttered Orrington trash plant
The former owners of the Orrington trash incinerator want a third party to manage the monthly fees municipalities are paying to the facility until a lawsuit...
Platte River Power Authority customers demand third party review of plans for more gas-fired energy
Community members in four Northern Colorado cities – Fort Collins, Longmont, Loveland and Estes Park - are criticizing their electric company's plan to...
Court places Tampa Electric on probation, orders $500K fine for fatal 2017 coal furnace accident
The utility will serve 36 months probation and implement a safety compliance plan designed by an independent third party auditor,...
NextEra Energy announces agreement to sell a 50% interest in an approximately 2,520-megawatt portfolio renewables project to a third party, highlighting the value of its best-in-class development program - Nov 30, 2021
JUNO BEACH, Fla., Nov. 30, 2021 /PRNewswire/ -- NextEra Energy, Inc. (NYSE: NEE) today announced that a subsidiary of NextEra Energy...
Last updated 2026-03-14