50 MW hybrid in Jackson, FL · In queue since September 2018 · Proposed COD July 2028
50 MW
Capacity
1
Components
Solar
7y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9y 10m
Facilities Study50%
Queue EntrySep 17, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-31
Project Details
State
FL
County
Jackson
Region
Southeast
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
Holmes Creek - Defuniak Springs (PS) 115kV line
Data Source
LBNL