74.5 MW hybrid in Putnam, FL · In queue since July 2018 · Proposed COD December 2023
74.5 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
5y 5m
Schedule
27 months past proposed COD
Construction75%
Queue EntryJul 30, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2023-12-30
Project Details
State
FL
County
Putnam
Region
Southeast
Developer
Third Party
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
Rice Sub
Data Source
LBNL