— Project Summary

Queue ID
FPL-339
Capacity
74.5 MW
Technology
Solar
Status
active
Location
Hendry, FL
Region
Southeast
Developer
FPL
IA Status
Facility Study

BetaActiveSolarFPLLBNL

74.5 MW generation in Hendry, FL · In queue since March 2018 · Proposed COD July 2027

74.5 MW

Capacity

1

Components

Solar

8 years

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

9y 4m

Facilities Study50%
Queue EntryMar 21, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-31

Project Details

State

FL

County

Hendry

Region

Southeast

Developer

FPL

Utility

Florida Power & Light

Entity

FPL

Point of Interconnection

Alva-Corbett 230kV

Data Source

LBNL

No news available for this project.