BetaActiveSolarFPLLBNL
74.5 MW generation in Brevard, FL · In queue since June 2017 · Proposed COD January 2026
74.5 MW
Capacity
1
Components
Solar
8y 9m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
8y 7m
Schedule
2 months past proposed COD
Facilities Study50%
Queue EntryJun 27, 2017
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-01-31
Project Details
State
FL
County
Brevard
Region
Southeast
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
Malabar-Midway 230kV
Data Source
LBNL
No news available for this project.