— Project Summary

Queue ID
FPL-276
Capacity
74.5 MW
Technology
Solar
Status
active
Location
Union, FL
Region
Southeast
Developer
FPL
IA Status
Facility Study

BetaActiveSolarFPLLBNL

74.5 MW generation in Union, FL · In queue since June 2017 · Proposed COD July 2028

74.5 MW

Capacity

1

Components

Solar

8y 9m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

11y 1m

Facilities Study50%
Queue EntryJun 27, 2017

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-31

Project Details

State

FL

County

Union

Region

Southeast

Developer

FPL

Utility

Florida Power & Light

Entity

FPL

Point of Interconnection

Bradford-Columbia 115kV

Data Source

LBNL

No news available for this project.