BetaActiveSolarFPLLBNL
74.5 MW generation in Manatee, FL · In queue since May 2016 · Proposed COD December 2026
74.5 MW
Capacity
1
Components
Solar
9y 10m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
10y 7m
Facilities Study50%
Queue EntryMay 9, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
FL
County
Manatee
Region
Southeast
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Point of Interconnection
Keentown-Manatee 230kV
Data Source
LBNL
No news available for this project.