— Project Summary

Queue ID
FPL-107
Capacity
1300 MW
Technology
Nuclear
Status
active
Location
Miami-Dade, FL
Region
Southeast
Developer
FPL
IA Status
Facility Study

BetaActiveNuclearFPLLBNL

1,300 MW generation in Miami-Dade, FL · In queue since August 2007 · Proposed COD June 2027

1,300 MW

Capacity

1

Components

Nuclear

18y 7m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

19y 10m

Facilities Study50%
Queue EntryAug 30, 2007

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

FL

County

Miami-Dade

Region

Southeast

Developer

FPL

Utility

Florida Power & Light

Entity

FPL

Point of Interconnection

Turkey Point Sub

Data Source

LBNL

No news available for this project.