Permian I Natural Gas
BetaActiveGas - Internal CombustionERCOTLive · ERCOT
1,247.4 MW generation in Pecos, Texas · In queue since January 2026 · Proposed COD June 2030
1,247.4 MW
Capacity
0
Components
2 months
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
4y 5m
Pre-Study0%
Queue EntryJan 13, 2026
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-06-30
Project Details
State
Texas
County
Pecos
Region
ERCOT
Developer
S&S Renewables, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap TNMP White Baker (38435)–Bottlebrush(38441) 345-kV double-circuit
Data Source
Live · ERCOT
No news available for this project.