Mistflower Energy Center Solar — Project Summary

Queue ID
ERCOT-30INR0088
Capacity
401.62 MW
Technology
Solar
Status
active
Location
Runnels, Texas
Region
ERCOT
Developer
Mistflower Energy Center LLC
IA Status

Mistflower Energy Center Solar

BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT

401.62 MW generation in Runnels, Texas · In queue since February 2026 · Proposed COD June 2030

401.62 MW

Capacity

0

Components

1 month

In Queue

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

4y 4m

Pre-Study0%
Queue EntryFeb 25, 2026

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-06-01

Project Details

State

Texas

County

Runnels

Region

ERCOT

Developer

Mistflower Energy Center LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345kV 60072 ODYSSEUS7A– 60040 BLF_CRK7A

Data Source

Live · ERCOT

No news available for this project.