Moon Hammer
ERCOT-30INR0077BetaActiveGasCombustion (gas) TurbineERCOTLive · ERCOT
1,300 MW generation in Wheeler, TX · In queue since January 2026 · Proposed COD November 2030
1,300 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
Signed Dec 2025
Interconnection Timeline
IA → COD
4y 11m
Total Duration
3 months
Construction0%
Queue EntryJan 13, 2026
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 19, 2025
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2030-11-30
Project Details
State
TX
County
Wheeler
Region
ERCOT
Developer
Moon Hammer LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV line between Tesla & Grey
Data Source
Live · ERCOT