MRR Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
500 MW generation in Pecos, Texas · In queue since July 2025 · Proposed COD July 2030
500 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
5 years
Pre-Study0%
Queue EntryJul 29, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-07-01
Project Details
State
Texas
County
Pecos
Region
ERCOT
Developer
BOULEVARD ASSOCIATES, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Solstice Substation #60384 -AEP
Data Source
Live · ERCOT
No news available for this project.