Lost Pines Power Park
880 MW generation in Bastrop, TX · In queue since June 2025 · Proposed COD December 2030
880 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
Signed Dec 2025
Queue → IA
6 months
IA → COD
5 years
Total Duration
6 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2030-12-15