Bell Song Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
167.6 MW generation in Jim Hogg, Texas · In queue since June 2025 · Proposed COD September 2029
167.6 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 3m
Pre-Study0%
Queue EntryJun 12, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-09-15
Project Details
State
Texas
County
Jim Hogg
Region
ERCOT
Developer
Bell Song Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV #80079 CRUCE7A - #80355 DELSOL7A ckt 1
Data Source
Live · ERCOT
No news available for this project.