Caldwell County Energy Center — Project Summary

Queue ID
ERCOT-30INR0031
Capacity
1500 MW
Technology
Gas
Status
active
Location
Caldwell, Texas
Region
ERCOT
Developer
Caldwell County Energy Center, LLC
IA Status

Caldwell County Energy Center

BetaActiveGas - Combustion (gas) TurbineERCOTLive · ERCOT

1,500 MW generation in Caldwell, Texas · In queue since February 2025 · Proposed COD April 2030

1,500 MW

Capacity

0

Components

1y 1m

In Queue

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

5y 2m

Pre-Study0%
Queue EntryFeb 3, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-04-30

Project Details

State

Texas

County

Caldwell

Region

ERCOT

Developer

Caldwell County Energy Center, LLC

Utility

Entity

ERCOT

Point of Interconnection

#7051 Misty Substation 345kV

Data Source

Live · ERCOT

No news available for this project.