Caldwell County Energy Center
BetaActiveGas - Combustion (gas) TurbineERCOTLive · ERCOT
1,500 MW generation in Caldwell, Texas · In queue since February 2025 · Proposed COD April 2030
1,500 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
5y 2m
Pre-Study0%
Queue EntryFeb 3, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-04-30
Project Details
State
Texas
County
Caldwell
Region
ERCOT
Developer
Caldwell County Energy Center, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
#7051 Misty Substation 345kV
Data Source
Live · ERCOT