Woodland Energy Storage
BetaActiveBatteryERCOTLBNL + Live
207.6 MW storage in Bosque, TX · In queue since December 2023 · Proposed COD October 2030
207.6 MW
Capacity
1
Components
Battery
2y 3m
In Queue
Facility Study
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
6y 10m
Facilities Study50%
Queue EntryDec 18, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-10-01
Project Details
State
TX
County
Bosque
Region
ERCOT
Developer
Woodland Energy Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
68040 Kopperl Substation 345kV
Data Source
LBNL + Live