BM Freestone Energy Center
BetaActiveGas - Combined-CycleERCOTLive · ERCOT
990.6 MW generation in Freestone, Texas · In queue since February 2026 · Proposed COD May 2029
990.6 MW
Capacity
0
Components
1 month
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 3m
Pre-Study0%
Queue EntryFeb 25, 2026
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-05-15
Project Details
State
Texas
County
Freestone
Region
ERCOT
Developer
Black Mountain Energy Storage II
Utility
—
Entity
ERCOT
Point of Interconnection
Loop Big Brown E to Navarro Ckt 1(PTI#3380-68091) and Big Brown W to Tarantulla Ckt 1 (PTI#3381-3344) at 31.813367° -96.147730°
Data Source
Live · ERCOT
No news available for this project.