Cerulean Unit 1 — Project Summary

Queue ID
ERCOT-29INR0248
Capacity
1200 MW
Technology
Gas
Status
active
Location
Victoria, Texas
Region
ERCOT
Developer
Brother 1, LLC
IA Status

Cerulean Unit 1

BetaActiveGas - Combined-CycleERCOTLive · ERCOT

1,200 MW generation in Victoria, Texas · In queue since January 2026 · Proposed COD March 2029

1,200 MW

Capacity

0

Components

2 months

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

3y 2m

Pre-Study0%
Queue EntryJan 26, 2026

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-03-30

Project Details

State

Texas

County

Victoria

Region

ERCOT

Developer

Brother 1, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap <345kV> <#5915> <South Texas Project SO_TEX__345A > - <#80286> <DULCE7A>

Data Source

Live · ERCOT

No news available for this project.