Copper Canyon Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
200.95 MW generation in Tom Green, Texas · In queue since January 2026 · Proposed COD December 2029
200.95 MW
Capacity
0
Components
2 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntryJan 26, 2026
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-21
Project Details
State
Texas
County
Tom Green
Region
ERCOT
Developer
Lightsource Renewable Energy US LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 6473 BENFICKL4A - 6442 REDCREEK4A
Data Source
Live · ERCOT