Brazos Energy Center 1
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
300.76 MW storage in McLennan, Texas · In queue since January 2026 · Proposed COD September 2029
300.76 MW
Capacity
0
Components
2 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 8m
Pre-Study0%
Queue EntryJan 13, 2026
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-09-18
Project Details
State
Texas
County
McLennan
Region
ERCOT
Developer
Ferrovial Energy US 1
Utility
—
Entity
ERCOT
Point of Interconnection
POSSUMTROT_5
Data Source
Live · ERCOT
No news available for this project.