Paint Brush PV4
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
251.5 MW generation in Coleman, Texas · In queue since December 2025 · Proposed COD December 2029
251.5 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4 years
Pre-Study0%
Queue EntryDec 2, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-31
Project Details
State
Texas
County
Coleman
Region
ERCOT
Developer
Renew Development HoldCo LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 1444 Brown Switch – 60040 Bluff Creek Switch
Data Source
Live · ERCOT