Sawtooth Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
201.36 MW generation in Runnels, Texas · In queue since November 2025 · Proposed COD August 2030
201.36 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
4y 9m
Pre-Study0%
Queue EntryNov 24, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-08-01
Project Details
State
Texas
County
Runnels
Region
ERCOT
Developer
Sawtooth Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap to the 345kV Odysseus (Bus#60072) to Bluff Creek (Bus #60040) line
Data Source
Live · ERCOT
No news available for this project.