Riviera Gas
BetaActiveGas - Combined-CycleERCOTLive · ERCOT
941.8 MW generation in Bell, Texas · In queue since November 2025 · Proposed COD June 2030
941.8 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
4y 7m
Pre-Study0%
Queue EntryNov 5, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-06-14
Project Details
State
Texas
County
Bell
Region
ERCOT
Developer
BKV-BPP Power
Utility
—
Entity
ERCOT
Point of Interconnection
3413 KNOB CREEK SWITCH SUBSTATION 345kV
Data Source
Live · ERCOT