Miller Bend Energy BESS
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
547.62 MW storage in Young, Texas · In queue since December 2025 · Proposed COD June 2029
547.62 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 6m
Pre-Study0%
Queue EntryDec 17, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-06-01
Project Details
State
Texas
County
Young
Region
ERCOT
Developer
Miller Bend Energy
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV (Bus1#1430) Graham SES to (Bus2#11050) Dusty Road
Data Source
Live · ERCOT