Velveteen Solar I
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
502.2 MW generation in Baylor, Texas · In queue since December 2025 · Proposed COD October 2029
502.2 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 10m
Pre-Study0%
Queue EntryDec 23, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-10-15
Project Details
State
Texas
County
Baylor
Region
ERCOT
Developer
Velveteen Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap into 6076 FOXTAIL- 6100 OKLAUNION
Data Source
Live · ERCOT
No news available for this project.