Two Step Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
402.06 MW generation in Ellis, Texas · In queue since December 2025 · Proposed COD September 2029
402.06 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 9m
Pre-Study0%
Queue EntryDec 17, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-09-17
Project Details
State
Texas
County
Ellis
Region
ERCOT
Developer
Two Step Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 1907 Venus - 68091 Navarro
Data Source
Live · ERCOT
News & Articles (1)Beta