Glass Mountain Wind 1
BetaActiveWind - Wind TurbineERCOTLive · ERCOT
511.5 MW generation in Reeves, Texas · In queue since January 2026 · Proposed COD December 2028
511.5 MW
Capacity
0
Components
2 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
2y 11m
Pre-Study0%
Queue EntryJan 13, 2026
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
Texas
County
Reeves
Region
ERCOT
Developer
Glass Mountain Wind, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 60404 SOLSTICE - 18669 TOYAHCRK_5
Data Source
Live · ERCOT
No news available for this project.