Star Of Texas Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
415 MW generation in Pecos, Texas · In queue since August 2025 · Proposed COD July 2029
415 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntryAug 18, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-07-01
Project Details
State
Texas
County
Pecos
Region
ERCOT
Developer
BOULEVARD ASSOCIATES, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap AEP Solstice (60404) to Bakersfield (76002) 345kV
Data Source
Live · ERCOT
News & Articles (1)Beta