Roan Solar Phase 2
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
205.9 MW generation in Sterling, Texas · In queue since October 2025 · Proposed COD December 2029
205.9 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 2m
Pre-Study0%
Queue EntryOct 21, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-15
Project Details
State
Texas
County
Sterling
Region
ERCOT
Developer
Roan Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Divide (#76090) to Sand Bluff Wind Farm (#59902) 345 kV
Data Source
Live · ERCOT
No news available for this project.