Gridline Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
400 MW generation in Crockett, Texas · In queue since August 2025 · Proposed COD July 2029
400 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntryAug 18, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-07-01
Project Details
State
Texas
County
Crockett
Region
ERCOT
Developer
Big Lake Ranch LLC
Utility
—
Entity
ERCOT
Point of Interconnection
76005 Schneeman Draw LCRA
Data Source
Live · ERCOT