Sweetheart BESS
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
310.16 MW storage in Young, Texas · In queue since August 2025 · Proposed COD February 2029
310.16 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 6m
Pre-Study0%
Queue EntryAug 26, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-02-14
Project Details
State
Texas
County
Young
Region
ERCOT
Developer
Sweetheart Energy, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV #1430 GRAHAM SES - # 17002 GARVEY ROAD SWITCH
Data Source
Live · ERCOT
No news available for this project.