Sweetheart Solar
301.14 MW generation in Young, Texas · In queue since August 2025 · Proposed COD February 2029
301.14 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-02-14
State
Texas
County
Young
Region
ERCOT
Developer
Sweetheart Energy, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV #1430 GRAHAM SES - # 17002 GARVEY ROAD SWITCH
Data Source
Live · ERCOT
Battery farms, the energy industry’s new darling, line up to enter Pacific NW
Utilities and independent energy companies have proposed a slew of standalone battery energy storage systems.
Details emerge about second large solar energy farm planned in Henderson County
A website indicates the Henderson County Solar project would be located on 541 acres along the Kentucky 425/South Bypass and nearby Lover's...
Details emerge about second large solar energy farm planned in Henderson County
A website indicates the Henderson County Solar project would be located on 541 acres along the Kentucky 425/South Bypass and nearby Lover's...
Last updated 2026-03-26