Big Watt Power Austin-1 — Project Summary

Queue ID
ERCOT-29INR0167
Capacity
448.98 MW
Technology
Gas
Status
active
Location
Caldwell, Texas
Region
ERCOT
Developer
Big Watt Power Austin-1 LLC
IA Status

Big Watt Power Austin-1

BetaActiveGas - Combined-CycleERCOTLive · ERCOT

448.98 MW generation in Caldwell, Texas · In queue since October 2025 · Proposed COD November 2028

448.98 MW

Capacity

0

Components

5 months

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 1m

Pre-Study0%
Queue EntryOct 3, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-01

Project Details

State

Texas

County

Caldwell

Region

ERCOT

Developer

Big Watt Power Austin-1 LLC

Utility

Entity

ERCOT

Point of Interconnection

Tapping the 345 kV Double circuit Line: Zorn (Bus# 7042) - Lytton Springs (Bus# 9074) and Zorn (Bus# 7042) - Austrop (Bus# 7040).

Data Source

Live · ERCOT

No news available for this project.